Technology
Assessment & Research (TA&R) Program
| Project Number |
627 |
| Date of Summary |
February 12, 2009 |
| Subject |
Assess/Develop Inspection Methodologies for Offshore Wind Turbine Facilities |
| Performing Activity |
Energo Engineering, Inc. |
| Principal Investigator |
Frank Puskar |
| Contracting Agency |
Minerals Management Service |
| Estimated Completion |
Completed February 10, 2009 |
| Description |
The project developed preliminary guideline Integrity Management (IM)
procedures for offshore wind turbine facilities appropriate for use in
US waters. These procedures include guidance on frequency and method of
inspection and address the platform structure, turbine tower, turbine
and housing, and turbine blades. |
| Progress |
|
| Report |
|
AA |
Inspection Methodologies for Offshore Wind Turbine Facilities, January 30, 2009 by Frank Puskar and Robert Sheppard, Energo Engineering, Inc., Houston, TX
|
|
|
|
|