Technology
Assessment & Research (TA&R) Program
| Project Number |
331 |
| Date of Summary |
March 01, 2003 |
| Subject |
Lifetime Cost of Sub-sea
Production Systems (JIP) |
| Performing Activity |
DNV/Goldsmith Consulting |
| Principal Investigator |
Riley Goldsmith, Remi Ericson
(DNV) |
| Contracting Agency |
Minerals Management Service |
| Estimated Completion |
October 2000 |
| Description |
The objective of this JIP was to
develop and demonstrate a structured probabilistic procedure for assessing
the lifetime risk and reliability of sub-sea production systems. System
costs will be evaluated with respect to safety, environmental, and
operational matters (OPEX, CAPEX, RISKEX, etc.). |
| Progress |
The first meeting of the JIP
participants was held on October 6, 1999. Work on a report and spreadsheet
program proceeded until the final scheduled meeting on September 26, 2000.
At that meeting, a draft final report and a draft spreadsheet were presented
for review. The project was completed in 2000 as a final report and
spreadsheet software were delivered to JIP participants at the conclusion of
the project. |
| Report |
AA
(280 pages) |
Lifetime Cost of Subsea
Production Systems, prepared for Subsea JIP, System Description & FMEA Rev.
2, Det Norske Veritas, June 2000. |
AB
(12 pages) |
Lifetime Cost of Subsea
Production Systems, prepared for Subsea JIP, Final Report Rev. 0, Det Norske
Veritas, November 2000. |
|
|
|
|