|
National Safety Alert
No. 7
July 28, 2003
SAFETY ALERT
Equipment Collapse During Workover Operation
Results in a Serious Near Miss
During a recent
workover operation using a jack-up lift boat positioned next to a satellite
well, a snubbing unit mast and gin pole assembly fell from the wellhead
after one of the assembly’s anchor points failed. The mast and gin pole
assembly was about 98 feet in length and weighed 36,000 pounds. The incident
caused relatively minor damage to equipment on an attending marine vessel
and the vessel’s bulkhead. Although no injuries, pollution, or significant
property damage resulted from the incident, the consequences could have been
much worse. The snubbing unit was located on the lift boat, and the unit’s mast assembly
was secured by guy wires extending to three fixed and one temporary anchor
points. The temporary anchor point was a set of two 4,000-pound cement
marine blocks placed in 8-9 feet of water on the sea floor. At some time
during the workover operation, the marine vessel, with a draft of 8 feet,
was positioned alongside the lift boat within 10 feet of the cement blocks
so that equipment on the vessel could be rearranged and offloaded. The
vessel worked in this location for approximately 1-1/2 hours and, because of
strong currents, used its reverse prop thrusters for stabilization. Within a
half hour of the vessel moving from that location, the snubbing unit mast
assembly fell.
The Bureau
investigation concluded that the immediate cause of the snubbing unit’s
collapse was the prop thrusters’ wash disturbance of the unconsolidated
seafloor under the cement blocks, resulting in the movement of the blocks
and a subsequent slackening of the attached cables. The failure of the
operator and contractor to adequately plan the snubbing operation and
address the potential hazards was evidenced by: 1) the use of an 8- foot
draft marine vessel in 8-9 feet of water, 2) operating the marine vessel in
close proximity to the temporary anchor for an extended period of time while
currents were running strong, and 3) the placement of the temporary anchor
on the seafloor where unstable conditions existed.
BOEMRE recommends that all operators and contractors thoroughly review their
procedures for workover operations. Operators and contractors should ensure
that they have evaluated all hazards associated with the planned activities
and have effectively implemented safe work practices to address these
hazards. For workovers in shallow water that will not be conducted from a
fixed platform, close attention should be paid to the hazards and safe
practices associated with anchor location and the operation of marine
vessels in the vicinity of snubbing units and other workover equipment.
For further information, please contact
Melinda Mayes, (703) 787-1064.
|