BOEMRE Approves Sixth Deepwater Drilling Permit
that Meets New Safety Standards
NEW ORLEANS – The Bureau of Ocean Energy
Management, Regulation and Enforcement (BOEMRE) today
approved a sixth deepwater drilling permit that complies
with rigorous new safety standards implemented in the
wake of the Deepwater Horizon explosion and resulting
oil spill. This includes satisfying the requirement to
demonstrate the capacity to contain a subsea blowout.
The approved permit is a revised permit to drill a new
well for Statoil Gulf of Mexico LLC’s Well #1 in
Alaminos Canyon Block 810 in 7,134 ft. water depth,
approximately 216 miles off the Texas coastline, south
of Texas City. “This permit is the sixth we have
approved since February 17, when industry demonstrated
that it had the capacity to handle subsea blowouts and
spills. Some say we are now proceeding too quickly; some
say we are still proceeding too slowly. The truth is, we
are proceeding as quickly as our resources allow to
approve permit applications that satisfy our rigorous
safety and environmental standards,” said BOEMRE
Director Michael R. Bromwich. “We will continue to do
so.”
Statoil’s Well #1 is a new well. The
operator had a rig under contract and an approved Permit
to Drill a New Well when activities were suspended due
to the temporary drilling suspensions imposed following
the Deepwater Horizon oil spill.
As part of its approval process, the
bureau reviewed Statoil’s containment capability
available for the specific well proposed in the permit
application. Statoil has contracted with the Helix Well
Containment Group to use its capping stack to stop the
flow of oil should a well control event occur. The
capabilities of the capping stack meet the requirements
that are specific to the characteristics of the proposed
well.
BOEMRE has worked diligently to help
industry adapt to and comply with new, rigorous safety
practices. These standards ensure that oil and gas
development continues, while also incorporating key
lessons learned from the Deepwater Horizon oil
spill. This new permit meets the new safety regulations
and information requirements in Notices to Lessees (NTL)
N06 and N10, and the Interim Final Safety Rule.
Today’s permit adds to the number of
permits that have been approved since new safety
regulations have been put in place. For a list of well
types, pending and approved permits, and information on
new safety regulations, go to:
http://www.gomr.boemre.gov/homepg/offshore/safety/well_permits.html.